- Renovations and new additions to 29-acre hospital complex including 111,800 SF of new construction, 24,700 major renovations, new central plant, and cooling tower
- Worked jointly with the design architect team and the hospital maintenance
- 8” public waterline extension
- Relocation of sanitary service force main while keeping service to residents
Challenges
- Extensive research to understand the puzzle of existing utilities
- Advised the team concerning the best options for abandonment, relocations, and expansion of existing utilities
- Maintained existing utility services to the Hospital while relocating the main powerhouse
- Pedestrian and vehicular traffic coordinated and maintained throughout the project
Categories
Office and Industrial
Date
2015
Project type
Office and Industrial
Duration
6 Months